Great work continues on our eight construction bond projects. Here is a summary of updates as presented to the school board at the May 21 meeting. Click on each project for details.

Sumner High School Phase 2 West Building 

  • Continue educational space needs research; anticipated completion in June
  • Continue schematic design (initial phase of architectural design process) through July
  • Completed geotechnical soil testing
  • Completed and reviewed floor plan concept 
  • Approved Hutteball + Oremus Architecture, Inc. as project architect (May 21 school board meeting)

Bonney Lake High School Expansion & Intersection Improvement

  • Continue educational space needs research; anticipated completion in June
  • Continue schematic design (initial phase of architectural design process) through August
  • Completed and reviewed floor plan concept 
  • Began BLHS/Mountain View MS intersection design 
  • Approved BCRA, Inc. as project architect (May 21 school board meeting)

New middle school in Tehaleh 

  • Continue educational space needs research; anticipated completion in June
  • Continue schematic design (initial phase of architectural design process) through September
  • Completed geotechnical soil testing
  • Approved McGranahanPBK as project architect (April 16 school board meeting)

Daffodil Valley Elementary and Donald Eismann Elementary 

  • Selected designer
  • Negotiating contract 
  • Preparing concepts 

Crestwood Elementary, Liberty Ridge Elementary and Tehaleh Heights Elementary 

  • Architect selections begin in June 

We thank our voters, who approved the construction bond in November, making these projects possible.